In 2005 as part of their ongoing rationalisation strategy, Symphony obtained detailed Planning Permission for a new 500,000sqft high bay warehouse distribution centre with offices on the site of the former Grimethorpe Colliery near Barnsley.
In 2006 GNA were appointed by Marshalls Construction (West Yorkshire) Ltd to take the project from the planning approved drawings through to completion on site.
GNA were later separately appointed to carry out the office fitting-out works.
As part of our ongoing work with Symphony, we have recently completed the latest factory for Symphony, see Symphony Phase Two >